Odoo implementation: steps and timelines

“How long does it take?” For an SMB starting from scratch with a few modules, allow two to six weeks between the first meeting and go-live. Here’s what happens during that time, and what we expect from you.

How long, in short

The orders of magnitude we observe:

  • Simple installation, 1 to 3 users, basic modules, clean data — 2 to 3 weeks.
  • Typical project, 4 to 10 users, with data migration and training — 4 to 6 weeks.
  • Project with migration from existing software, or with additional modules — 6 to 10 weeks.

It isn’t full-time work for that whole period: most of the delay comes from back-and-forth approvals and your team’s availability. A project where answers come quickly finishes quickly.

Step 1 — The scoping meeting

One hour, online or on site. We look at how you work today: who does what, with which tools, where things get stuck. We barely talk about Odoo at this stage.

What comes out of it: the list of modules you really need, an inventory of the data to bring over, and a written quote. Free and with no commitment.

Step 2 — Installation and hosting

We set up your server, install Odoo, configure your domain name and security certificate, then put local and off-site backups in place. This step happens on our side, without tying up anyone on yours.

Allow one to two days. At the end, you have an address and a login.

Step 3 — Configuring your reality

This is the heart of the work, and what sets a real project apart from a demo: your Quebec taxes, your invoice numbering, your payment terms, your document templates with your logo, each person’s access rights, your product or activity categories.

We move forward in blocks and you approve as we go. Plan for one to three weeks, depending on the number of modules.

Step 4 — Importing your data

Customers, suppliers, products, stock, opening balances. We first import into a test environment to see what snags, fix it, then start over cleanly.

This is where your involvement matters most. Nobody knows your data better than you: which customers are still active, which products no longer sell, which price is the right one. A list cleaned up beforehand saves several days.

Step 5 — Training your team

Two to four hours depending on the package, online or on site, with your real data — not with sample data. We go over the operations you’ll do every week: create a quote, turn it into an invoice, receive a payment, pull a report.

Training happens before go-live, never after. A system delivered without training is a system the team works around in the first busy week.

Step 6 — Go-live and the first weeks

On switchover day: final import, opening balances, and you start working in Odoo. We stay close at hand during the first days, when the real questions come up.

Plan for two to four weeks during which the old system remains available read-only. It’s a safety net that costs nothing and reassures everyone.

What derails a schedule

In order of frequency, based on our projects:

  • Data in poor shape. By far the leading cause. Three customer files that don’t match get sorted out before you start, not during.
  • Pending decisions. “We’ll see later how we number invoices” holds up an entire step.
  • Scope creep. Adding payroll along the way is another project — better to deliver, then add.
  • The timing. An implementation in the middle of peak season always drags on.

Our way of limiting the damage: a written scope from the quote onward, and delivery in blocks rather than a big reveal at the end.